Chester highway superintendent provides report on major winter storm

CHESTER — Chester Highway Superintendent Charles Dazelle, speaking Monday at 4 p.m. after being at it for 33 hours straight, said the Jan. 25 storm cleanup overall went well.

“Everything went [well]. We didn’t have any calls — no accidents or medical. No calls at all. No trees down,” Dazelle said, adding, “We’re done.” He said the crew now had to go home and snowplow their own driveways.

With a crew of three, the town hired out White Wolf’s 10-wheeler to help with the cleanup, a contractor they’ve used before. He said their truck can hold more sand, as the biggest one in Chester has six wheels.

Chester has one F250, a four-wheel drive that was repaired just before the storm, and two F-550 dump trucks with sanders. He said a new F-550 is on order to replace one from 2015.

“There’s about 10 years on a pickup’s life expectancy,” he said.

He said the storm came down fast, and there was light snow on top of ice in some areas, and a couple of trucks slipped. By the end, Chester had 18 to 20 inches overall.

“All in all, it went [well]. The Select Board was happy we didn’t get any calls,” he said.

Dazelle also talked about $1.3 million the department has received in grants to engineer Johnson Hill Road and for paving and drainage to finish Blandford Road. “A lot of people use that road,” he said.

This post was originally published on this site